In April 2024, ABO-ERG conducted a hydrogeological study with a view to redeveloping the Musinens neighbourhood in the municipality of Valserhône (01).
This study was conducted in parallel with a geotechnical study carried out at the G1-G2-AVP stage.
This project included the construction of five separate lots, each comprising basements with footprints ranging from 2,100 to 3,700 m².
After analysing the hydrogeological data, it became apparent that most of the structures intersected, either frequently or occasionally, an aquifer present at the level of the limestone formations.
In this sense, the objectives of this study were to:
· Present the geological and hydrogeological context of the site,
· Specify the hydrodynamic characteristics of the formations encountered and potentially affected by the project.,
· Estimate the characteristic groundwater levels at the site,
· Assess the drainage flow rates and the range of pumping operations associated with the proposed water level reduction solutions.,
· Present the administrative context related to the project.
Agency:
Date of completion:
Place of production:
Work completed:
Relevant qualifications:
Mission details:
Solutions provided by:

In April 2024, ABO-ERG conducted a hydrogeological study with a view to redeveloping the Musinens neighbourhood in the municipality of Valserhône (01).
This study was conducted in parallel with a geotechnical study carried out at the G1-G2-AVP stage.
This project included the construction of five separate lots, each comprising basements with footprints ranging from 2,100 to 3,700 m².
After analysing the hydrogeological data, it became apparent that most of the structures intersected, either frequently or occasionally, an aquifer present at the level of the limestone formations.
In this sense, the objectives of this study were to:
· Present the geological and hydrogeological context of the site,
· Specify the hydrodynamic characteristics of the formations encountered and potentially affected by the project.,
· Estimate the characteristic groundwater levels at the site,
· Assess the drainage flow rates and the range of pumping operations associated with the proposed water level reduction solutions.,
· Present the administrative context related to the project.
Agency:
Date of completion:
Amount excluding VAT:
Place of production:
Type of mission according to standard 94500:
Work completed:
Relevant qualifications:
Mission details: